SECURITY OF PAYMENT · AUSTRALIAN CAPITAL TERRITORY
The ACT’s Building and Construction Industry (Security of Payment) Act 2009 follows the NSW model closely, including the 27 to 31 December business day pause. Payment is now due within 15 business days of a claim, tightened by amendments that took effect on 11 March 2024. Here are the ACT deadlines, what your claim must say, and what to do when SOPA doesn’t fit.
Can you use it? Three quick checks
Was it construction work, or goods and services related to construction? Was the work carried out in the ACT? Are you within 12 months of the work being done or the goods and services being supplied, whichever is later? Three yeses and you can probably serve a payment claim.
A no doesn’t mean you can’t get paid. It just means the fast-track SOPA process isn’t the right tool, and you recover the money under your contract instead.
ACT deadlines at a glance
All timeframes are business days, which in the ACT exclude weekends, public holidays and 27 to 31 December, the same as NSW. These are the defaults under the Act; where your contract sets an earlier date for a step, the earlier date applies, so check it too.
Who can claim
Head contractors, subcontractors, suppliers, plant hirers and consultants
Claim window
On the last day of each calendar month, or an earlier day in the month if your contract says so, as long as work has been done or goods supplied. The Act also sets an outer limit on how long after the work a claim can be made, so check it before serving a late claim
Payment schedule
Within the earlier of the time your contract requires and 10 business days after the claim is given. If they don’t give one, they become liable to pay the claimed amount on the due date
Payment due (contract silent)
The earlier of 15 business days after the payment claim is given and the day payment becomes payable under the contract, following the amendments that took effect on 11 March 2024
Adjudication, schedule disputed
Apply within 10 business days of receiving the payment schedule. If they gave a schedule but didn’t pay by the due date, the window is 20 business days after the due date
Adjudication, no schedule or payment
Give notice within 20 business days of the due date, which gives them 5 business days to provide a payment schedule, then apply within 10 business days
How SOPA works in the ACT
Serve a payment claim that identifies the work, states the amount and says it’s made under the Act. Keep proof of when and how you served it.
If they won’t pay in full, they must give you a payment schedule with reasons within 10 business days, or sooner if your contract requires it.
If you dispute the schedule, or they don’t pay, apply for adjudication through an authorised nominating authority.
An independent adjudicator with relevant expertise decides the dispute on the documents. If the adjudicated amount isn’t paid, you can get an adjudication certificate and file it in court as a judgment debt.
WORKING FOR A HOMEOWNER?
No, the ACT excludes work on the respondent’s own home
The Act does not apply to a construction contract for residential building work on the part of any premises the respondent lives in, or intends to live in, where a resident owner is a party. There are two things worth knowing. If the contract also covers work that is not on their residence, that other work is still subject to the Act. And the exclusion does not reach work done under an owner-builder licence. The Act applies normally to residential investment properties, landlords, strata bodies corporate, developers, builders, subcontractors, consultants and suppliers.
What an ACT payment claim must include
The construction work or related goods and services the claim is for
The amount you’re claiming
A statement that it’s made under the Building and Construction Industry (Security of Payment) Act 2009 (ACT)
REQUIRED WORDING
“This is a payment claim made under the Building and Construction Industry (Security of Payment) Act 2009 (ACT)”
The ACT requires the endorsement, so every ACT payment claim must include this statement or words to the same effect. You can add it to your invoice template so your invoices can work as payment claims. Queensland is the exception: there, no wording is needed.
When SOPA isn’t the right tool
SOPA is fast but strict. It’s not the best fit when you’ve missed the claim or adjudication window, the job wasn’t construction work, or you want to keep the client and just need them to pay.
You can still recover the money under your contract. BetterDebt follows up your customer by email, SMS and phone, offers easy ways to pay and pauses for genuine disputes. See our fees page for current pricing.
Frequently asked questions
When exactly can I serve a payment claim in the ACT?
On the last day of each calendar month, or an earlier day in that month if your contract nominates one, provided you’ve done work or supplied goods. You can also claim on the day a construction contract is terminated. If SOPA doesn’t fit, a letter of demand is usually the next step.
What if I missed the SOPA deadlines?
You don’t lose the debt. You lose the fast-track adjudication for that claim. You can usually still recover the money under your contract with a letter of demand, a collector like BetterDebt, or a tribunal. Note that in the ACT a civil dispute under $25,000 goes to ACAT, not the Magistrates Court, which only hears civil matters from $25,000 up.
What changed on 11 March 2024?
The due date for payment became the earlier of 15 business days after the claim is given and the contractual due date, and payment claims moved to a calendar month basis. If your contract was drafted before that, its payment terms may no longer be enforceable to the extent they run longer.
Do I need a lawyer for adjudication?
The Act doesn’t require you to use a lawyer, but adjudication has strict rules. For large or complex claims, get legal advice.
Sources
ACT Government: Security of payments
ACT Government: Security of Payment Act information (PDF)
ACT legislation: Building and Construction Industry (Security of Payment) Act 2009
ACT Magistrates Court: Civil matters
Last checked 21 November 2026. General information, not legal advice. BetterDebt is a debt collector, not a law firm.
Owed money on a construction job?