Security of Payment Acts: the deadlines in every state

Security of Payment Acts: the deadlines in every state

Security of Payment Acts: the deadlines in every state

Every state and territory has its own Security of Payment Act, and the deadlines are different in each one. Get the wrong number and your claim is out of time. This page puts all eight side by side, then links to a full guide for your state. Figures were checked on 21 November 2026 against each government’s own source.

Can you use it? Three quick checks

Was it construction work, or goods and services related to construction? Which state or territory was the work carried out in? Are you still inside that state’s claim window? Get those three right and you can work out which Act applies and what your deadlines are.

A no doesn’t mean you can’t get paid. It just means the fast-track statutory process isn’t the right tool, and you recover the money under your contract instead.

Deadlines by state and territory

Payment schedule is how long the other side has to respond to your claim. Adjudication is your window to escalate. The NT counts working days and works on a different model entirely. Your contract can set shorter periods for some steps, so always check it as well as the Act.

Payment schedule 10 business days · Adjudication 10 business days from the schedule · The Act covers owner-occupier work

Payment schedule 10 business days · Adjudication 10 business days · Payment hard-capped at 20 business days since 15 April 2026

Payment schedule 15 business days · Adjudication 20 or 30 business days depending on the pathway · No claim wording required

Payment schedule 15 business days · Adjudication 20 business days · Payment due 20 business days head contract, 25 subcontract

Payment schedule 15 business days · Adjudication 15 business days from the schedule · Payment due 15 business days

Payment schedule 10 business days, or 20 against a homeowner · Adjudication 10 business days · Claim window 12 months

Payment schedule 10 business days · Adjudication 10 business days · Payment due 15 business days since 11 March 2024

No payment schedule regime · Adjudication 65 working days from when the payment dispute arises · Counts working days

The four steps, wherever you are

  • Serve a payment claim that identifies the work and states the amount. In every state except Queensland it must also say it’s made under the Act. Keep proof of when and how you served it.

  • If they won’t pay in full, they must respond with a payment schedule giving reasons, within that state’s deadline. Miss it and they can become liable for the full amount claimed.

  • NSW covers owner-occupier construction contracts, and has since 1 March 2021. Tasmania covers homeowner work too, but gives the homeowner 20 business days instead of 10 to respond. Victoria, Queensland, South Australia and the ACT all exclude work on a home the owner lives in or intends to live in, so on a standard home job the Act is not available to you. Western Australia excludes home building work for an individual below the $500,000 threshold, but applies above it. The NT works on implied contract terms rather than carving out a residential class. Check your state’s page before serving a claim on a homeowner.

  • An adjudicator decides on the documents, usually within about 10 business days. If the adjudicated amount isn’t paid, you can get a certificate and file it in court as a judgment debt.

WORKING FOR A HOMEOWNER?

The answer depends on your state, and it’s the most misunderstood part

NSW covers owner-occupier construction contracts, and has since 1 March 2021. Tasmania covers homeowner work too, but gives the homeowner 20 business days instead of 10 to respond. Victoria, Queensland and South Australia all exclude domestic building work for a resident owner, so on a standard home job the Act is not available to you. Western Australia excludes home building work for an individual below the $500,000 threshold, but applies above it. The NT implies terms into the contract rather than carving out a residential class. Check your state’s page before serving a claim on a homeowner.

What a payment claim must include

  1. The construction work or related goods and services the claim is for

  2. The amount you’re claiming

  3. In every state except Queensland, a statement that it’s made under that state’s Act

QUEENSLAND IS THE EXCEPTION

Queensland dropped the “made under the Act” wording on 17 December 2018. Every other state and territory with a payment claim regime still requires it

That means an ordinary Queensland invoice can be a payment claim with statutory consequences, in both directions. If you work across state lines, the safe habit is to endorse every claim, every time. The endorsement does no harm in Queensland and is mandatory everywhere else.

When the statutory route isn’t the right tool

These Acts are fast but strict. They’re not the best fit when you’ve missed the claim or adjudication window, the job was excluded residential work, or you want to keep the client and just need them to pay.

You can still recover the money under your contract. BetterDebt follows up your customer by email, SMS and phone, offers easy ways to pay and pauses for genuine disputes. See our fees page for current pricing.

Frequently asked questions

Which state’s Act applies to my job?

The one where the construction work was carried out, not where you or your client are based. Every Act is limited to work in its own state or territory, so a Sydney business doing a job in Brisbane is under the Queensland BIF Act. If the statutory route doesn’t fit, a letter of demand is usually the next step.

Which state gives me the longest time to apply for adjudication?

The Northern Territory, by a wide margin: 65 working days from when the payment dispute arises. Queensland gives 30 business days on some pathways. Most of the east coast gives you just 10 business days from the payment schedule, which is why so many claims are filed out of time.

Do the Christmas shutdown rules differ?

Yes, and it catches people out. NSW and the ACT exclude 27 to 31 December from business days. Victoria and Queensland exclude the whole period from 22 December to 10 January. That can push a January deadline weeks later than you’d expect, so check your state’s rule before assuming a date.

What changed recently?

Victoria rebuilt its Act on 15 April 2026, including a hard 20 business day payment cap that applies to contracts you already signed. The ACT tightened its payment due date on 11 March 2024. WA passed an amendment Act on 21 October 2026 that has mostly not commenced yet. We re-check every figure on these pages twice a year.

Sources

NSW Government: Making a payment claim

QBCC: Request payment

Victorian Building Authority: Changes to the SOP Act

Building Standards Tasmania: Security of payment

Last checked 21 November 2026. Every figure on this page is sourced from the relevant government or legislation page, linked on each state’s own guide. General information, not legal advice. BetterDebt is a debt collector, not a law firm.