SECURITY OF PAYMENT · TASMANIA
Tasmania’s Building and Construction Industry Security of Payment Act 2009 gives contractors, subbies and suppliers a fast, legal way to get paid. Unlike most states, Tasmania does cover work for homeowners, it just gives them longer to respond. Here are the Tasmanian deadlines, what your claim must say, and what to do when SOPA doesn’t fit.
Can you use it? Three quick checks
Was it building or construction work, or related goods and services? Was the work carried out in Tasmania? Are you within 12 months of when the work was finished, unless your contract says otherwise? Three yeses and you can probably serve a payment claim.
A no doesn’t mean you can’t get paid. It just means the fast-track SOPA process isn’t the right tool, and you recover the money under your contract instead.
TAS deadlines at a glance
All timeframes are business days as the Act defines them. These are the defaults; your contract can set different dates for some steps, so check it too. Note the longer payment schedule window when you’re claiming against a homeowner.
Who can claim
Head contractors, subcontractors, suppliers, plant hirers and consultants
Claim window
On or after the reference date in your contract. The Act also sets an outer limit on how long after the work you can claim, so check the current Act or the Building Standards Tasmania guidance before serving a late claim
Payment schedule
Within 10 business days of the claim being served. That extends to 20 business days where the claim relates to a residential structure, the respondent owns the land and isn’t a building practitioner. Miss it and the whole claimed amount becomes payable
Payment due (contract silent)
10 business days after the payment claim is served, unless your contract sets a date
Adjudication, schedule disputed
Apply within 10 business days of receiving the payment schedule. If they gave a schedule but didn’t pay the scheduled amount, the window is 20 business days after the due date
Adjudication, no schedule or payment
Give notice within 20 business days of the due date, allow 5 business days for a late payment schedule, then apply
How SOPA works in TAS
Serve a payment claim that identifies the work, states the amount and says it’s made under the Act. Keep proof of when and how you served it.
If they won’t pay in full, they must give you a payment schedule with reasons within 10 business days, or 20 business days if they’re a homeowner who isn’t a building practitioner.
If you dispute the schedule, or they don’t pay, apply for adjudication through a nominating authority authorised under the Tasmanian Act.
If the adjudicator determines an amount is owed, it must be paid within 5 business days of the determination unless the adjudicator sets another date. If it isn’t paid, you can have the amount become a judgment debt.
WORKING FOR A HOMEOWNER?
Yes, Tasmania covers homeowner work
Tasmania is one of the few states where the Act still applies when you’re claiming against a homeowner. The trade-off is time: where the claim relates to a residential structure, the respondent owns the land and isn’t a registered building practitioner, they get 20 business days to serve a payment schedule instead of 10. Diarise the longer date, because applying for adjudication too early can sink the application.
What a TAS payment claim must include
A description of the building or construction work, or the related goods and services, the claim is for
The amount you’re claiming
A statement that it’s made under the Building and Construction Industry Security of Payment Act 2009 (Tas)
REQUIRED WORDING
“This is a payment claim made under the Building and Construction Industry Security of Payment Act 2009 (Tas)”
Tasmania requires the endorsement, so every Tasmanian payment claim must include this statement or words to the same effect. You can add it to your invoice template so your invoices can work as payment claims. Queensland is the exception: there, no wording is needed.
When SOPA isn’t the right tool
SOPA is fast but strict. It’s not the best fit when you’ve missed the claim or adjudication window, the job wasn’t building or construction work, or you want to keep the client and just need them to pay.
You can still recover the money under your contract. BetterDebt follows up your customer by email, SMS and phone, offers easy ways to pay and pauses for genuine disputes. See our fees page for current pricing.
Frequently asked questions
Do I get 10 or 20 business days for the payment schedule?
Twenty applies only where all three conditions are met: the claim relates to a residential structure, the respondent owns the land, and the respondent isn’t a building practitioner. Commercial work, and work for a builder or developer, is 10. If you’re unsure, wait for the longer period before applying for adjudication. If SOPA doesn’t fit, a letter of demand is usually the next step.
What if I missed the SOPA deadlines?
You don’t lose the debt. You lose the fast-track adjudication for that claim. You can usually still recover the money under your contract with a letter of demand, a collector like BetterDebt, or court (the Tasmanian Magistrates Court hears minor civil claims up to $15,000, and civil claims from $15,001 to $50,000).
Can I send my normal invoice as a payment claim?
Yes, if it describes the work, states the amount, includes the statement that it’s made under the Act and is served on or after the reference date.
Do I need a lawyer for adjudication?
The Act doesn’t require you to use a lawyer, but adjudication has strict rules. For large or complex claims, get legal advice.
Sources
Building Standards Tasmania: Security of payment, making a claim
Building Standards Tasmania: Building dispute payments
Tasmanian legislation: Building and Construction Industry Security of Payment Act 2009
Magistrates Court of Tasmania: Civil division
Last checked 21 November 2026. General information, not legal advice. BetterDebt is a debt collector, not a law firm.