Security of Payment Act VIC: how subbies get paid

Security of Payment Act VIC: how subbies get paid

Security of Payment Act VIC: how subbies get paid

Victoria rebuilt its Security of Payment Act on 15 April 2026. Payment terms are now capped at 20 business days, business days pause from 22 December to 10 January, and respondents can’t invent new reasons at adjudication. Here are the current Victorian deadlines, what your claim must say, and what to do when SOPA doesn’t fit.

Can you use it? Three quick checks

Was it construction work, or goods and services related to construction? Was the work carried out in Victoria? Are you inside the claim window your contract sets, or within 6 months of practical completion for a final claim? Three yeses and you can probably serve a payment claim.

A no doesn’t mean you can’t get paid. It just means the fast-track SOPA process isn’t the right tool, and you recover the money under your contract instead.

VIC deadlines at a glance

All timeframes are business days, which in Victoria exclude weekends, public holidays and the period from 22 December to 10 January. These are the defaults under the Act as amended on 15 April 2026; your contract can set shorter periods for some steps, so check it too.

Who can claim

Head contractors, subcontractors, suppliers, plant hirers and consultants

Claim window

On the dates your contract sets. Reference dates no longer trigger entitlement, and a final payment claim can be served up to 6 months after practical completion, extended from 3 months on 15 April 2026

Payment schedule

Within 10 business days of receiving your claim. If they don’t give one and don’t pay, they can become liable for the full amount claimed

Payment due (contract silent)

10 business days after the claim is served. Any contract term requiring payment later than 20 business days after service is void to that extent, so 20 business days is a hard cap

Adjudication, schedule disputed

Apply within 10 business days of receiving the payment schedule

Adjudication, no schedule or payment

Serve a notice of intention to apply, which gives them 5 business days to provide a payment schedule, then apply within 10 business days

How SOPA works in VIC

  • Serve a payment claim that identifies the work, states the amount and says it’s made under the Act. Keep proof of when and how you served it.

  • If they won’t pay in full, they must give you a payment schedule with reasons within 10 business days. Since 15 April 2026 they cannot add new reasons later at adjudication.

  • If you dispute the schedule, or they don’t pay, apply for adjudication through an authorised nominating authority (ANA) within 10 business days, and serve a copy on the respondent within 3 business days.

  • The respondent has 5 business days to respond, and the adjudicator must decide within 10 business days. Determinations can no longer be sent for review. If the adjudicated amount isn’t paid, you can get an adjudication certificate and file it in court as a judgment debt.

WORKING FOR A HOMEOWNER?

No, Victoria excludes most homeowner work

Unlike NSW, the Victorian Act does not apply to a domestic building contract between a builder and a building owner for domestic building work, unless that owner is in the business of building residences. So on a standard home job for an owner-occupier, SOPA is not available to you and you recover under the contract instead. It still works normally down the chain, between a builder and their subbies.

What a VIC payment claim must include

  1. The construction work or related goods and services the claim is for

  2. The amount you’re claiming

  3. A statement that it’s made under the Building and Construction Industry Security of Payment Act 2002 (Vic)

REQUIRED WORDING

“This is a payment claim made under the Building and Construction Industry Security of Payment Act 2002 (Vic)”

Victoria still requires the endorsement, so every Victorian payment claim must include this statement or words to the same effect. You can add it to your invoice template so your invoices can work as payment claims. Queensland is the exception: there, no wording is needed.

When SOPA isn’t the right tool

SOPA is fast but strict. It’s not the best fit when you’ve missed the claim or adjudication window, the job was domestic building work for an owner-occupier, or you want to keep the client and just need them to pay.

You can still recover the money under your contract. BetterDebt follows up your customer by email, SMS and phone, offers easy ways to pay and pauses for genuine disputes. See our fees page for current pricing.

Frequently asked questions

What actually changed in Victoria on 15 April 2026?

Payment terms are capped at 20 business days, reference dates are gone, business days now pause from 22 December to 10 January, respondents can’t raise new reasons at adjudication, the review of determinations is abolished, and there’s a new statutory right to claim release of performance security. The changes apply to existing contracts too, not just new ones. If SOPA doesn’t fit, a letter of demand is usually the next step.

What if I missed the SOPA deadlines?

You don’t lose the debt. You lose the fast-track adjudication for that claim. You can usually still recover the money under your contract with a letter of demand, a collector like BetterDebt, or court (the Victorian Magistrates’ Court hears claims up to $100,000).

Can I send my normal invoice as a payment claim?

Yes, if it identifies the work, states the amount, includes the statement that it’s made under the Act and is served at the time your contract allows.

Do I need a lawyer for adjudication?

The Act doesn’t require you to use a lawyer, but adjudication has strict rules and the 10 business day window is short. For large or complex claims, get legal advice.