SECURITY OF PAYMENT · NORTHERN TERRITORY

Security of Payments NT: how subbies get paid

Security of Payments NT: how subbies get paid

Security of Payments NT: how subbies get paid

The Northern Territory works differently from every eastern state. There are no payment claims and payment schedules here. Instead, the Construction Contracts (Security of Payments) Act 2004 implies fair payment terms into your contract where it’s silent, and lets either party take a “payment dispute” to adjudication. You get far longer to apply than anywhere else: 65 working days. Here’s how it works.

Can you use it? Three quick checks

Was it construction work, or goods and services related to construction? Was the work carried out in the Northern Territory? Has a payment dispute arisen, meaning your claim was rejected or went unpaid when it was due? Three yeses and you can probably apply for adjudication.

A no doesn’t mean you can’t get paid. It just means the adjudication route isn’t open yet, and you recover the money under your contract instead.

NT deadlines at a glance

The NT counts working days, not “business days” as the eastern states define them. The one deadline below that is fixed by statute is the adjudication window. The periods for responding to a claim and for payment are set by your contract, and where it is silent the Act implies them — those implied periods have been amended, and a lot of published guidance still quotes superseded figures, so confirm them against the current Act before you rely on a date.

Who can claim

Either party to a construction contract can refer a payment dispute, including head contractors, subcontractors, suppliers and consultants

When a dispute arises

A payment dispute arises when the amount claimed is due to be paid under the contract and is not paid in full, or when the claim is rejected or wholly or partly disputed

Responding to a claim

There is no payment schedule regime in the NT. Where your contract sets out how a claim is disputed, that governs. Where it is silent, the Act implies a process in Schedule 1 — check the current version of the Act for the period that applies

Payment due

As your contract provides. Where the contract is silent the Act implies a payment period, and a term that defers payment too far is read down to a shorter one. Both figures are set by the Act, so confirm them against the current version

Apply for adjudication

Within 65 working days after the payment dispute arises. This was increased from 90 calendar days, so older guides quoting 90 days are out of date

Adjudication response

The respondent responds within the period set by the Act once served with the adjudication application

How adjudication works in the NT

  • Make your claim under the contract. If the contract is silent on process, the Act’s implied terms in Schedule 1 fill the gap.

  • A payment dispute arises the moment the claim is rejected, disputed, or unpaid at its due date. Diarise that date, because the whole clock runs from it.

  • Within 65 working days, prepare a written application for adjudication and serve it on the other party and on a prescribed appointer, such as Master Builders NT or the Law Society Northern Territory.

  • The respondent then has its chance to respond within the period the Act sets. The adjudicator decides on the documents, and a determination can be enforced as a judgment debt. “Pay if paid” and “pay when paid” clauses are prohibited and cannot be used against you.

WORKING FOR A HOMEOWNER?

Check your contract first, and whether you’ve opted out

The NT Act implies terms into construction contracts rather than carving out a residential class the way the eastern states do, so the question to ask first is what your contract actually says. Parties to high-value contracts can also opt out of the statutory adjudication regime if the contract contains a compliant alternative dispute mechanism, so read the contract before assuming adjudication is available. Get advice if the job is a home for an owner-occupier.

What an NT payment claim must include

  1. A description of the construction work or related goods and services the claim is for

  2. The amount you’re claiming, and when it falls due under the contract

  3. No statement that it’s made under the Act. The NT has no endorsement requirement, because it has no statutory payment claim regime

NO WORDING REQUIRED

The NT has no payment claim endorsement, because it has no payment claim and payment schedule regime at all

This is the biggest practical difference between the NT and the east coast. Nothing you write on an invoice triggers a statutory clock here. What matters is the date your payment fell due under the contract, because that is when the payment dispute arises and the 65 working day adjudication window starts running.

When adjudication isn’t the right tool

Adjudication is effective but formal. It’s not the best fit when you’ve passed the 65 working day window, your contract validly opted out of the regime, or you want to keep the client and just need them to pay.

You can still recover the money under your contract. BetterDebt follows up your customer by email, SMS and phone, offers easy ways to pay and pauses for genuine disputes. See our fees page for current pricing.

Frequently asked questions

Is it 90 days or 65 working days to apply for adjudication?

65 working days. Section 28 of the Act was amended, and the current version in force counts 65 working days from when the payment dispute arises. A lot of online guidance still quotes the old 90 calendar days, which would have you applying too late. If adjudication doesn’t fit, a letter of demand is usually the next step.

What if I missed the adjudication window?

You don’t lose the debt. You lose the adjudication route for that dispute. You can usually still recover the money under your contract with a letter of demand, a collector like BetterDebt, or a tribunal. In the NT a claim under $25,000 goes to NTCAT; the Local Court hears debt claims from $25,000 to $250,000.

Why doesn’t the NT use payment claims and payment schedules?

The NT follows what’s called the West Coast model, like WA’s old Construction Contracts Act. Rather than creating a statutory claim and response sequence, it implies fair payment terms into contracts that are silent and gives both parties a route to rapid adjudication once a dispute arises. It’s less prescriptive, and the windows are longer.

Do I need a lawyer for adjudication?

The Act doesn’t require you to use a lawyer, but adjudication has strict rules and the application has to be properly prepared. For large or complex claims, get legal advice.