Security of Payment Act QLD: how subbies get paid

Security of Payment Act QLD: how subbies get paid

Security of Payment Act QLD: how subbies get paid

Queensland runs on the Building Industry Fairness (Security of Payment) Act 2017, known as the BIF Act. It works differently from the other states in one important way: your ordinary invoice can be a payment claim, with no special wording needed. Here are the Queensland deadlines, what your claim must contain, and what to do when the BIF Act doesn’t fit.

Can you use it? Three quick checks

Was it construction work, or goods and services related to construction? Was the work carried out in Queensland? Are you within 6 months of when the work was last carried out? Three yeses and you can probably give a payment claim.

A no doesn’t mean you can’t get paid. It just means the fast-track BIF Act process isn’t the right tool, and you recover the money under your contract instead.

QLD deadlines at a glance

All timeframes are business days, which in Queensland exclude weekends, public holidays and the period from 22 December to 10 January. These are the defaults under the BIF Act; your contract can set shorter periods for some steps, and the QBCC Act caps payment terms, so check both.

Who can claim

Head contractors, subcontractors, suppliers, plant hirers and consultants

Claim window

One payment claim per reference date, given within 6 months of when the work was last carried out or the related goods and services were last supplied. A final payment claim has its own longer window

Payment schedule

Within 15 business days of the claim being given, or sooner if your contract says so. If they don’t give one and don’t pay, they can become liable for the full amount claimed

Payment due (contract silent)

10 business days after the claim is given. The QBCC Act also caps payment terms at 15 business days for commercial building contracts and 25 business days for subcontracts, and anything longer is void

Adjudication, schedule disputed

Apply within 30 business days of receiving the payment schedule. If they gave a schedule but didn’t pay the scheduled amount, the window is only 20 business days after the due date

Adjudication, no schedule or payment

Apply within 30 business days after the later of the due date for payment and the last day they could have given a payment schedule

How the BIF Act works in QLD

  • Give a payment claim that identifies the work, states the amount and requests payment. No “made under the Act” wording is needed in Queensland. Keep proof of when and how you gave it.

  • If they won’t pay in full, they must give you a payment schedule with reasons within 15 business days. Queensland removed the second-chance notice in 2018, so a missed schedule has immediate consequences.

  • If they won’t pay in full, they must give you a payment schedule with reasons within 15 business days. Queensland does not give the second-chance notice step that NSW and several other states have, so a missed schedule has immediate consequences.

  • The respondent responds within 10 business days for standard claims, and the adjudicator decides within 10 business days of the response. The adjudicated amount must be paid within 5 business days. If it isn’t, you can file the adjudication certificate in court as a judgment debt.

WORKING FOR A HOMEOWNER?

No, Queensland excludes resident owners

The progress payment chapter of the BIF Act does not apply to a contract for domestic building work where a resident owner is a party, so on a standard home job for an owner-occupier the BIF Act is not available to you. Owner-builders and building contractors are not resident owners for this exclusion. The Act still works normally down the chain, between a builder and their subbies.

What a QLD payment claim must include

  1. The construction work or related goods and services the claim is for

  2. The amount you’re claiming, and a request for payment

  3. Nothing else. No statement that it’s made under the Act, which is what makes Queensland different

NO WORDING REQUIRED

In Queensland, any invoice that identifies the work, states the amount and requests payment is a payment claim

Queensland dropped the “made under the Act” requirement on 17 December 2018. That cuts both ways: your invoices can work as payment claims without changing anything, but every invoice you send may also be a payment claim with statutory consequences, and every invoice you receive may be one too. If you work across states, endorse everything anyway.

When the BIF Act isn’t the right tool

The BIF Act is fast but strict. It’s not the best fit when you’ve missed the claim or adjudication window, the job was domestic building work for a resident owner, or you want to keep the client and just need them to pay.

You can still recover the money under your contract. BetterDebt follows up your customer by email, SMS and phone, offers easy ways to pay and pauses for genuine disputes. See our fees page for current pricing.

Frequently asked questions

Do I really not need the “made under the Act” wording in Queensland?

Correct. Section 68 only requires a written document that identifies the work, states the amount claimed and requests payment, and a document headed “invoice” satisfies the request for payment. Adding the endorsement does no harm, and it’s sensible if you also work in other states. If the BIF Act doesn’t fit, a letter of demand is usually the next step.

What if I missed the adjudication window?

You don’t lose the debt. You lose the fast-track adjudication for that claim. Missed deadlines are the single biggest reason Queensland adjudication applications get thrown out. You can usually still recover the money under your contract with a letter of demand, a collector like BetterDebt, or court (QCAT hears minor debt claims up to $25,000).

Which deadline applies to me, 20 or 30 business days?

If they gave you a payment schedule for less than you claimed, it’s 30 business days from receiving it. If they gave you a schedule and then didn’t pay the scheduled amount, it’s only 20 business days from the due date. If they gave you nothing, it’s 30 business days from the later of the due date and the last day a schedule was due.

Do I need a lawyer for adjudication?

The Act doesn’t require you to use a lawyer, but adjudication has strict rules. For large or complex claims, get legal advice.

Sources

QBCC: Request payment

QBCC: Business days and the holiday period

Queensland legislation: Building Industry Fairness (Security of Payment) Act 2017

QCAT: Debt dispute process

Last checked 21 November 2026. General information, not legal advice. BetterDebt is a debt collector, not a law firm.