SECURITY OF PAYMENT · NEW SOUTH WALES
The NSW Security of Payment Act gives contractors, subbies and suppliers a fast, legal way to get paid for construction work. Serve a payment claim and the other side must respond within strict deadlines, or they can become liable for the full amount. Here are the NSW deadlines, what your claim must say, and what to do when SOPA doesn’t fit.
Can you use it? Three quick checks
Was it construction work, or goods and services related to construction? Was the work done in NSW? Are you within 12 months of when the work was last done, or a longer period your contract allows? Three yeses and you can probably serve a payment claim.
A no doesn’t mean you can’t get paid. It just means the fast-track SOPA process isn’t the right tool, and you recover the money under your contract instead.
NSW deadlines at a glance
All timeframes are business days, which in NSW exclude weekends, public holidays and 27 to 31 December. These are the defaults under the Act; your contract can set different dates for some steps, so check it too.
Who can claim
Head contractors, subcontractors, suppliers, plant hirers and consultants
Claim window
One claim per month, from the last day of the month the work was done (or on the dates your contract sets). The work must have been carried out within the last 12 months, or a longer period if your contract allows
Payment schedule
Within 10 business days of receiving your claim. If they don’t give one and don’t pay, they can become liable for the full amount claimed
Payment due (contract silent)
Head contractor: 15 business days · Subcontractor: 20 business days · Subcontractor on exempt residential work: 10 business days
Adjudication, schedule disputed
Apply within 10 business days of receiving the payment schedule
Adjudication, no schedule or payment
Give notice within 20 business days of the due date, allow 5 business days, then apply within 10 business days
How SOPA works in NSW
Serve a payment claim that identifies the work, states the amount and says it’s made under the Act. Keep proof of when and how you served it.
If they won’t pay in full, they must give you a payment schedule with reasons within 10 business days.
If you dispute the schedule, or they don’t pay, apply for adjudication through an authorised nominating authority (ANA).
An adjudicator must decide within 10 business days of accepting the application, unless the parties agree to more time. If the adjudicated amount isn’t paid, you can get an adjudication certificate and file it in court as a judgment debt.
WORKING FOR A HOMEOWNER?
Yes, NSW covers owner-occupier work
In NSW, the Act also applies to owner-occupier construction contracts, meaning building work on a home where the owner lives or plans to live. Special rules and timeframes apply, so check them before serving a claim on a homeowner.
What a NSW payment claim must include
The construction work or related goods and services the claim is for
The amount you’re claiming
A statement that it’s made under the Building and Construction Industry Security of Payment Act 1999 (NSW)
REQUIRED WORDING
“This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 NSW”
For contracts entered into from 21 October 2019, every NSW payment claim must include this statement, or words to the same effect. You can add it to your invoice template so your invoices can work as payment claims.
When SOPA isn’t the right tool
SOPA is fast but strict. It’s not the best fit when you’ve missed the claim or adjudication window, the job wasn’t construction work, or you want to keep the client and just need them to pay.
You can still recover the money under your contract. BetterDebt follows up your customer by email, SMS and phone, offers easy ways to pay and pauses for genuine disputes. See our fees page for current pricing.
Frequently asked questions
Do I need a written contract to use SOPA in NSW?
No. The Act covers construction contracts and other arrangements, including verbal ones. You still need to prove what was agreed, so keep quotes, messages and photos. If SOPA doesn’t fit, a letter of demand is usually the next step.
What if I missed the SOPA deadlines?
You don’t lose the debt. You lose the fast-track adjudication for that claim. You can usually still recover the money under your contract with a letter of demand, a collector like BetterDebt, or court (the NSW Local Court hears claims up to $100,000).
Can I send my normal invoice as a payment claim?
Yes, if it identifies the work, states the amount, includes the statement that it’s made under the Act and is served at the right time (generally one claim per month).
Do I need a lawyer for adjudication?
The Act doesn’t require you to use a lawyer, but adjudication has strict rules. For large or complex claims, get legal advice.
Sources
NSW Government: Making a payment claim
NSW Fair Trading: Recent changes to Security of Payment laws
NSW Fair Trading: Security of Payment Guide (PDF)
Resolution Institute: NSW adjudication process
Last checked 20 November 2026. General information, not legal advice. BetterDebt is a debt collector, not a law firm.
Owed money on a construction job?
If SOPA isn’t the right fit, BetterDebt can follow up your customer by email, SMS and phone, and pause for genuine disputes.